<strong id="2rwti"></strong><tr id="2rwti"><tr id="2rwti"></tr></tr><strong id="2rwti"></strong><strong id="2rwti"></strong><strong id="2rwti"><strong id="2rwti"></strong></strong><listing id="2rwti"></listing><strong id="2rwti"><output id="2rwti"><tr id="2rwti"></tr></output></strong><strong id="2rwti"><strong id="2rwti"></strong></strong> <strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"></strong><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"></output></strong><strong id="2rwti"></strong><listing id="2rwti"><output id="2rwti"></output></listing><listing id="2rwti"><output id="2rwti"></output></listing><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><listing id="2rwti"><output id="2rwti"></output></listing><strong id="2rwti"></strong> <listing id="2rwti"></listing><listing id="2rwti"></listing><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"></output></strong><strong id="2rwti"></strong><output id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"><strong id="2rwti"></strong></strong><strong id="2rwti"><strong id="2rwti"></strong></strong><strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><strong id="2rwti"><output id="2rwti"></output></strong>

公司脫硫塔一次性吊裝成功

日前,隨著現場吊裝總指揮的一聲令下,公司12萬噸/年石油焦煅燒項目煙氣除塵脫硫處理裝置第三段一次吊裝就位成功。整個吊裝過程平穩有序,就位不差分毫,達到預期目的。

公司12萬噸/年石油焦煅燒項目煙氣除塵脫硫處理裝置是公司石油焦煅燒工藝中的重要組成系統。脫硫塔總高為66米,塔體直徑4.5米,塔體重量為200噸,共分為三段制作吊裝。此裝置采用濕電除塵脫硫一體設備系統,具有塔液一體、占地面積小、產生的漿液容易控制等優點,有利于提高生產效率、優化現場管理。自今年10月份起,公司項目部及施工單位團結協作,克服工期緊、任務重、場地狹小、低溫降雨等諸多不利因素,積極協調各方關系,調整施工方案,采取有效措施,搶工期抓進度,有力確保了脫硫塔土建基礎施工順利完成,并進行了后續主塔的鋼結構安裝等工作,為保障脫硫塔順利吊裝奠定了結實基礎。

本次煙氣除塵脫硫處理裝置的安裝就位,是保證石油焦煅燒車間按期點火、順利運行的首要條件,脫硫塔順利運行后可實現超凈排放。

?
新聞中心
国产精品爽爽爽不卡不卡
<strong id="2rwti"></strong><tr id="2rwti"><tr id="2rwti"></tr></tr><strong id="2rwti"></strong><strong id="2rwti"></strong><strong id="2rwti"><strong id="2rwti"></strong></strong><listing id="2rwti"></listing><strong id="2rwti"><output id="2rwti"><tr id="2rwti"></tr></output></strong><strong id="2rwti"><strong id="2rwti"></strong></strong> <strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"></strong><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"></output></strong><strong id="2rwti"></strong><listing id="2rwti"><output id="2rwti"></output></listing><listing id="2rwti"><output id="2rwti"></output></listing><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><listing id="2rwti"><output id="2rwti"></output></listing><strong id="2rwti"></strong> <listing id="2rwti"></listing><listing id="2rwti"></listing><strong id="2rwti"></strong><strong id="2rwti"><output id="2rwti"></output></strong><strong id="2rwti"></strong><output id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"><strong id="2rwti"></strong></strong><strong id="2rwti"><strong id="2rwti"></strong></strong><strong id="2rwti"><output id="2rwti"><noframes id="2rwti"><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><output id="2rwti"><output id="2rwti"></output></output><strong id="2rwti"><output id="2rwti"></output></strong><noframes id="2rwti"><strong id="2rwti"><output id="2rwti"></output></strong>